New Construction Electrical Contractor in Las Vegas
Fowler Electric wires new builds across the Las Vegas Valley for general contractors, developers, and owner-builders: complete power distribution, lighting, low voltage, and utility coordination, delivered on schedule and to code. Licensed and bonded (NV License #0079908 · NV License #0087194), serving the valley for more than 25 years.
What a Licensed Electrical Contractor Delivers on a New Build
On a new build, the electrical contractor owns everything from the utility handoff to the last trim plate. That scope is bigger than most schedules give it credit for, and it touches nearly every other trade on the job. A complete new construction electrical package from Fowler Electric covers:
- Power distribution. Service entrance, metering, panelboards and subpanels, feeders, and branch circuits sized to the actual connected load, not a guess. See our panel installation work for how we handle distribution equipment.
- Lighting systems. Interior and exterior lighting, controls, dimming, and title-compliant energy layouts, installed to the photometric intent on the plans.
- Low voltage rough-in. Data, communications, security, and AV pathways roughed in while the walls are open, so the low-voltage trades land clean.
- Backup and standby power. Generator transfer equipment and standby circuits where the plans call for them.
- Device and fixture trim. Outlets, switches, smoke and CO detection, and final installation of every scheduled fixture.
Every conductor, termination, and piece of gear goes in per the adopted National Electrical Code and the Southern Nevada amendments that Clark County and the valley jurisdictions layer on top of it. That local-amendment layer is where out-of-market electricians get red-tagged. We work under it every week.
How We Work With General Contractors: The 5-Phase Model
New construction electrical fails in predictable places: scope gaps at bid time, missed rough-in windows, failed inspections, and nobody answering the phone after closeout. Our collaboration model is built to close each of those holes in order.
Phase 1: Pre-Construction and Value Engineering
We review the plan set before we price it. That means flagging conflicts between the electrical sheets and the mechanical and structural drawings, catching under-sized services before they become change orders, and proposing value-engineering swaps (fixture packages, circuiting consolidations, conduit routing) that cut cost without cutting what the inspector or the end user will notice. You get a bid built from the drawings, with exclusions stated in plain language instead of buried.
Phase 2: Scheduling and Trade Coordination
Electrical touches framing, plumbing, HVAC, drywall, and finish work, in that order, and a missed window ripples through all of them. We commit to rough-in and trim dates against your master schedule, sequence our crews around the concrete and framing milestones, and coordinate directly with your mechanical and plumbing subs on shared wall and ceiling space so the drywall date holds. On production work we plan by phase and lot release, so crew size scales with your closing schedule instead of lagging it.
Phase 3: Rough-In and Quality Control to the NEC and Local Amendments
Rough-in is where code compliance is actually built, long before an inspector sees it. Our foremen run internal QC walks against the currently adopted NEC edition and the Southern Nevada amendments before we ever call for inspection: box fill, conductor protection, grounding electrode work, panel clearances, and the local-amendment items that generic checklists miss. The goal is a first-pass green tag, because a failed rough inspection costs the whole job days, not just the electrician.
Phase 4: Inspections and Commissioning
We call for and attend our own inspections, walk the inspector through the work, and turn corrections around immediately when they happen. On commercial projects we handle panel labeling, breaker scheduling, load verification, and the commissioning documentation the owner's team needs at turnover. Power gets energized in coordination with the utility, not as an afterthought.
Phase 5: Warranty Support
After certificate of occupancy, we stay reachable. Warranty items get a scheduled response, not a voicemail loop, and because the same company that built the system services it, there is no diagnostic learning curve. GCs who build with us repeatedly tell us this phase is why they came back.
Building in Las Vegas: The Local Process
Two agencies control every new-build electrical timeline in the valley: the building department that holds your permit and the utility that energizes your service. Knowing how both actually operate is worth more than any line item on a bid.
Clark County Building Department
Unincorporated Clark County (which includes most of the Enterprise, Spring Valley, and Paradise growth corridors) runs permitting through the county's online Citizen Access Portal: plan sets are submitted electronically as PDFs, reviews are assigned by document type, and permit status is trackable throughout. Per the Clark County Building and Fire Prevention department (accessed July 2026), commercial permits are issued only to licensed contractors, and inspections can be scheduled online around the clock, by phone at (702) 455-3000, or in person at the Field Services counter at 4701 W. Russell Road. New construction finals also stack additional clearances (fire, drainage, utility approvals) ahead of sign-off, so sequencing those requests correctly matters. We pull our own permits, manage plan-review corrections, and schedule every rough and final inspection so your superintendent does not have to learn the portal. Builds inside the cities of Las Vegas, Henderson, and North Las Vegas run through those jurisdictions' own building departments, and we work in all of them; see our service areas.
NV Energy Service Coordination
Getting permanent power is its own project with its own clock. NV Energy runs new service through its online New Construction Portal (accessed July 2026), a six-phase process with published timelines:
| NV Energy phase | Published typical duration |
|---|---|
| Initiation (application and documents) | 2 to 4 weeks |
| Design | 6 to 8 weeks |
| Service inspection | 24 to 48 hours |
| Scheduling | 2 to 4 weeks |
| Construction | 4 to 6 weeks |
| Meter set | About 72 hours |
Add that up and utility power is a months-long track that has to start early, not after drywall. One recent process change worth knowing: effective January 12, 2026, NV Energy requires the meter set application to be submitted before the service (lateral) inspection to the customer panel is requested (source: NV Energy New Construction Portal, accessed July 2026). An electrical contractor who submits complete applications, builds the service to spec, and passes the utility inspection on the first visit is the cheapest schedule insurance a GC can buy. We run that coordination as part of scope on every new build.
Scheduling Around the Summer Heat
From June through September, valley attics run far hotter than the 110 degree afternoons outside, and OSHA-smart crews rough in attic and rooftop work in early-morning blocks. We plan for it: summer rough-ins start at first light, attic pulls are crewed heavier and rotated, and exterior gear set is sequenced around concrete and roofing so nobody is landing conductors on a 140 degree deck at 3 PM. A contractor who pretends July in Las Vegas is like July anywhere else will either blow your schedule or burn out their crews. We have built through more than 25 valley summers and schedule accordingly.
Residential vs Commercial New Construction Scope
The two halves of new-build work look similar on a schedule and nothing alike in the field, and we staff them differently.
Residential new construction covers custom homes, small-lot infill, casitas and ADUs, and production housing phases. The work is single-phase 120/240V service, load calculations that now have to anticipate EV charging and modern AC tonnage, whole-home surge protection, and finish-grade trim work that a homeowner will inspect with their eyes an inch from the plate. Our residential team handles it, and homes we wire are ready for the EV charger question before the buyer asks it.
Commercial new construction means shell buildings, ground-up retail and office, restaurants, and light industrial: three-phase services, switchgear, transformer coordination with the utility, egress and site lighting, and commissioning paperwork. Our commercial division runs this work, and when a shell we wired later needs a build-out, our tenant improvement crews already know what is behind the walls.
What New Construction Electrical Work Costs
Every bid is priced from your actual plan set, but the national benchmarks are useful for early budgeting. National cost guides such as HomeAdvisor put new construction electrical wiring at $3 to $5 per square foot, with the rough-in portion alone at $2 to $4 per square foot (accessed July 2026), and Fixr lists a comparable $3 to $6 per square foot range for new home wiring (accessed July 2026). Those are national figures, not Las Vegas prices, and commercial work prices by scope, not square footage alone. Fowler Electric bids from plans and specs and quotes the exact price up front, before work begins, so the number on the bid is the number on the invoice. For a broader look at local pricing, see our Las Vegas electrician cost guide.
Licensing You Can Verify
Fowler Electric holds two active Nevada contractor licenses (NV License #0079908 · NV License #0087194), issued and bonded through the Nevada State Contractors Board. You can confirm both in the NSCB's public license lookup at nvcontractorsboard.com, which exists so owners and GCs can verify that a contractor is licensed and in good standing before signing anything. We put the numbers on the page because we want you to run them. The company has served the Las Vegas Valley for more than 25 years, and our office is local: 6675 W Pebble Rd, Las Vegas, NV 89139.
Send Us Your Plans
If you are a general contractor, developer, or owner-builder with a project in Las Vegas, Henderson, North Las Vegas, or anywhere in the valley, send us the plan set. We return plan-and-spec bids with clean scope language, real exclusions, and dates we intend to hit. Call 702-778-4346 or request a bid online, and if you are earlier than drawings, we are glad to talk pre-construction budgeting from schematic design.
To get the fastest turnaround on a bid, include the electrical sheets and panel schedules, the relevant spec divisions, the site plan showing the utility point of connection, and your target rough-in and turnover dates. If any of those are still in flux, send what you have. We would rather flag a service-size problem at bid time than discover it in plan review. Office hours: Mon-Fri 7:00am-4:30pm · 24/7 Emergency Service.
Frequently Asked Questions
Do you bid new construction projects from plans and specs?
Yes. Send your plan set and specifications through our contact page or call 702-778-4346 and we will return a written plan-and-spec bid with clear scope language and stated exclusions. We price from the drawings, flag plan conflicts and value-engineering opportunities we find during takeoff, and quote the exact price up front, so the number on the bid is the number on the invoice. If you are earlier than drawings, we can help with pre-construction budgeting from schematic design.
Who pulls the electrical permit on a new build in Clark County?
The electrical contractor of record pulls the electrical permit. Clark County issues commercial permits only to licensed contractors, and permitting runs through the county's online Citizen Access Portal, where plan sets are submitted electronically and inspections are scheduled online, by phone, or in person. Fowler Electric handles permit submittal, plan-review corrections, and every rough and final inspection as part of a new construction scope, in unincorporated Clark County as well as the cities of Las Vegas, Henderson, and North Las Vegas. Call 702-778-4346 with questions about permitting on your project.
How long does it take NV Energy to connect power to a new building in Las Vegas?
Plan on months, not weeks. NV Energy runs new service through its online New Construction Portal in six phases: initiation, design, service inspection, scheduling, construction, and meter set. The published phase timelines add up to roughly three to five months for a project that moves without corrections, with design alone typically taking six to eight weeks, while the final meter set takes about 72 hours once everything upstream is complete. An electrical contractor who submits complete applications and passes the utility service inspection on the first visit is the best schedule protection you can buy. Fowler Electric manages NV Energy coordination as part of scope on every new build. Call 702-778-4346 to talk through utility timelines for your project.
Do you handle both residential and commercial new construction?
Yes. On the residential side Fowler Electric wires custom homes, production housing phases, infill projects, casitas, and ADUs, including load planning for modern AC and EV charging. On the commercial side we build shell buildings, ground-up retail and office, restaurants, and light industrial projects, including three-phase services, switchgear, site lighting, and commissioning documentation. The company has served the Las Vegas Valley for more than 25 years and holds active Nevada electrical contractor licensing. Call 702-778-4346 for a bid on either type of project.